FACTORY INSPECTORATE

SL.NO

ACTIVITY / SERVICES RENDERED

FORM TO BE SUBMITTED

AUTHORITY / OFFICES TO BE APPROACHED

TIME LIMIT

FACTORIES ACT, 1948.

1

Permission / approval of plans for the construction of / extension of factory building and installation of machinery

Form IC

Chief Inspector of Factories

Within One month from the date of receipt of application complete in all respects.

2

Registration and grant of licence for the new factories

Form 2

Chief Inspector of Factories

Within One month from the date of receipt of application complete in all respects

3

Renewal of license of the running factories

Form 2

 

Chief Inspector of Factories

Within One month from the date of receipt of application complete in all respects

4

Issue of NOC for the units not covered under any category notified under Section 85(i) of the Factories Act, 1948.

Application in plain paper.

Chief Inspector of Factories

Within 7 days from the date of receipt of application

5

Registration and issue of certificate for the use of a boiler under the Indian Boilers Act, 1923.

Application in the plain paper accompanied by manufacturers Boilers Book

Chief Inspector of Factories and Boilers

Within one month from the date of presentation of Boilers and steam pipe line for inspection

6

Renewal of certificate for use of a boiler on the expiry of a period for which it was granted.

Application in plain paper accompanied by required fees.

Chief Inspector of Factories and Boilers

Within one month from the date of receipt of application

7

Medical examination of workers after remittance of payment of medical examination fee and submission of challan receipt.

Application in Plain Paper

Joint Chief Inspector of Factories and Boilers / Medical Inspector of Factories.

Within one month from the date of receipt of the application. An average of 100 workers will be examined.

8

Cancellation of Registration on the request of the Management.

Closure report as prescribed in the Rule (2) along with original licence and copy of settlement details if any, with respect to the retrenched workers.

Chief Inspector of Factories

Within One month from the date of receipt of Closure Report and Original License.